Work in Progress: Working on pile caps and grade beams.  Plan to start column line 17 (Southern most column line) next week. Started working on forming elevator #2 (South). Pouring elevator #1 second lift (North) today. Continuing the installation of the basement…

Read More »

3/24- Smith Hall Renovation Updates

March 24, 2016

Work in Progress: First floor restroom and offices duct layout is complete with HVAC piping and duct installation has begun. Room 101 & 104 electrical rough-in is at 90% complete. Machine Shop electric panel installed and completed on Saturday 3/19. Room 223 electrical…

Read More »

3/24- Cunningham Hall Renovation Updates

March 24, 2016

Work in Progress: Steam piping in the 3rd floor east mechanical room is 20% complete. Steam condensate lines for the steam station and AHU#1 are in progress. Started installation of piping and duct work from AHU#2 in the 3rd floor west mechanical room to the addition has…

Read More »

91´«Ã½ÔÚÏß Researchers Publish Breakthrough in Leading Scientific Journal

March 24, 2016

Senior Research Fellow Quan Li, Ph.D., and his research group at 91´«Ã½ÔÚÏß’s Liquid Crystal Institute®, in the College of Arts and Sciences, have published a research article in the March 17 issue of Nature that could lead to a variety of breakthrough device…

Read More »

3/17- Cunningham Hall Renovation Updates

March 17, 2016

Work in Progress: Chilled water service in the 3rd floor east mechanical room is 95% complete by EOB on 3/18.  Will be ready for cooling system startup on 4/15. Currently insulating the chilled water pipes in the 3rd floor wast mechanical room. Steam reducing station…

Read More »

3/17- Smith Hall Renovation Updates

March 17, 2016

Work in Progress: New restroom plumbing rough-in nearly complete. Sheet metal duct rough-in has begun on the first floor and the new restroom areas. Electrical floor boxes are 75% complete in 223. Sanitary drain and toilet carriers are complete in the second floor. 3rd…

Read More »

April 6 is 91´«Ã½ÔÚÏß Day at the Cleveland International Film Festival

March 16, 2016

91´«Ã½ÔÚÏß Day at the Cleveland Film Festival (CIFF) is slated for April 6 at Tower City Cinemas in downtown Cleveland. 91´«Ã½ÔÚÏß is a sponsor of the festival and members of the 91´«Ã½ÔÚÏß community will receive $2 off any ticket to a film showing on that day. Kent…

Read More »

91´«Ã½ÔÚÏß's Wick Poetry Center to Expand Traveling Stanzas Project With $125,000 in New Funding From Knight Foundation

March 16, 2016

The Wick Poetry Center at 91´«Ã½ÔÚÏß will expand its successful Traveling Stanzas project with $125,000 in new funding from the John S. and James L. Knight Foundation, as part of its Knight Arts Challenge. The Knight Arts Challenge funds ideas that…

Read More »

3/11- Cunningham Hall Renovation Update

March 11, 2016

Work in Progress: Work continues on the chilled water service lines in the 3rd floor east mechanical room. Work continues on the steam service in the 3rd floor west mechanical room. Installation of AHU#1 in the 3rd floor east mechanical room continues. Unit #4 duct tie in…

Read More »

3/11- Smith Hall Renovation Update

March 11, 2016

Work in Progress: Continuing the wall framing and electrical rough-in in room 101, 104, & 223. Wall framing, electrical & plumbing rough-in continue in the new first floor restrooms. Electrical floor box layout and core drilling has begun in 223. Continuing the…